While Kulin Group is proud of the reputation they have forged and the projects they have been involved in over the years, there are always some projects that stand out. Whether it is the prestige of the project, the evolution in Kulin Groups capabilities, complexity of the works or the ongoing satisfaction of the client that has allowed Kulin Group to maintain a site presence over an extended period, (in some case years), attached is a snapshot of several successful projects undertaken by Kulin Group. Some of our projects: |
Water Treatment Facilities
"Kulin Group has steadily expanded to be regarded as one of the most respected Specialist Contractors in Australia..."
For information on our services click here. |
|
|
|
Client |
John Holland Group |
Location |
Process Buildings - Pluto LNG Project, Burrup Peninsula, Western Australia |
Scope |
Supply & Install Waterproof Membrane System |
|
In 2009 Kulin Group where engaged to supply and install in excess of 6,000 m2 of an EPDM sheet membrane water proofing system to the roofs associated with the sub stations and FAR buildings on site at the Pluto LNG Project on the Burrup Peninsula. Learn More... |
|
|
|
|
Client |
Mirvac |
Location |
Leighton Beach Apartments - Stage 1 - Perth, Western Australia |
Scope |
AFS Logicwall Installation |
|
In 2009 Kulin Group were awarded a portion of the construction works associated with the first stage of the Leighton Beach Apartments by Mirvac on the foreshore of Leighton Beach. Given the prestige of this project for Mirvac, along with it being the first multilevel construction project in the new Leighton Beach precinct it was paramount that the installation of the AFS Logicwall system be carried out in a safe and proficient manner. Learn More... |
|
|
|
|
Client |
Fremantle Ports |
Location |
Kwinana Bulk Terminal Berth 2 - Kwinana, Western Australia |
Scope |
Concrete Repair & Supply & Installation of an Impressed Current Cathodic Protection System. |
|
In 2005 Kulin Group were awarded the contract to carry out the concrete repair works to the soffit and beams and the design and installation of an Impressed Current Cathodic Protection system to the KBT Wharf in Kwinana. As this wharf was to remain in continuous service for the duration of the originally proposed 6 month works program, it was necessary for Kulin Group to carry out these works to the highest standard possible without impacting on the Wharf operations. Learn More... |
|
|
|
|
Client |
Ausclad Group of Companies (AGC) |
Location |
Pluto LNG Project - Burrup Peninsula, Western Australia |
Scope |
Precision Grouting Installation |
|
In 2008 Kulin Group where engaged to undertake a large portion of the precision grouting works associated with the process equipment being installed on site at the Pluto LNG Project. Learn More... |
|
|
|
|
Client |
Department of Infrastructure, Planning & Environment |
Location |
Stokes Hill Wharf - Darwin, Northern Territory |
Scope |
Supply & Installation of an Impressed Current Cathodic Protection System |
|
In 2003 Kulin Group were chosen to supply and install an Impressed Current Cathodic Protection system for the Stokes Hill Wharf in Darwin Northern Territory. With the Stokes Hill Wharf being an integral part of Northern Territory infrastructure, it was the responsibility of Kulin Group to carry out these works to the highest standard possible. Learn More... |
|